To add further and to more precise, the issue is:
In CM01[or in any capacity evaluation tcode], In a particular maonths load[Period] the opeartion from different month is showing up.
For example: if Period[month] 06 is veiwed of a Workcenter load, a line[load appears], whose earliest date is in 7th month[01.07.2014].
I expected to see, only Workcenters scheduled in 6th month to show up in the load evaluation.
Please look at the screen shot.
Regards,
Avinash