Hi Ramagiri,
Is not that possible at planning lebel? They maintain the SAP PP process as below:
One order comes from customer of Material 'A' for 50000pcs for dtd. 10.05.2014. After that production team put that quantity in PIR(MD61) then they run the MRP(MD02) after that they run stock requirement list(MD04) & there create a planned order of 50000pcs.
But they want to plan 50000pcs in two different work center on the same day.
You suggest me earlier for production order but their requirement is planned order lebel.
Regards,
Biplab Malakar