Hi everyone,
looking for a bit of guidance of EV calculation from an SKF POC.
I've setup the following structure:
- L1 WBS - Measurement Method % Progress SKF Version Z01 Weight 100
- L2 WBS - Measurement Method % Progress SKF Version Z01 Weight 50
- L2 WBS - Measurement Method % Progress SKF Version Z01 Weight 50
- NWA 1 Measurement Method Cubic Metres SKF Version Z01 Weight 20
- NWA 2 Measurement Method Cubic Metres SKF Version Z01 Weight 80
The version Z01 is using EV basis as Weighted
The following has been carried out:
- Planned revenue against L1 WBS as billing WBS
- Planned costs using ECP against NWAs
- Actual start dates have been entered
- Planning QTYs of skf on the NWAs and have
- Posting actuals against these skfs.
When running CNE1 the POC is calculated however plan/actual EV BCWS BCWP is not showing in the EV reports.
If I change the version and MM to Estimation on the L1 L2 WBSs and update the POC in CNPAWB these are calculated.
Any pointers would be great.
Cheers