Hi everyone,

 

looking for a bit of guidance of EV calculation from an SKF POC.

 

I've setup the following structure:

 

  • L1 WBS - Measurement Method % Progress SKF Version Z01 Weight 100

 

  • L2 WBS - Measurement Method % Progress SKF Version Z01 Weight 50

 

  • L2 WBS - Measurement Method % Progress SKF Version Z01 Weight 50

 

  • NWA 1 Measurement Method Cubic Metres SKF Version Z01 Weight 20

 

  • NWA 2 Measurement Method Cubic Metres SKF  Version Z01 Weight 80

 

The version Z01 is using EV basis as Weighted

 

The following has been carried out:

 

  • Planned revenue against L1 WBS as billing WBS
  • Planned costs using ECP against NWAs
  • Actual start dates have been entered
  • Planning QTYs of skf on the NWAs and have
  • Posting actuals against these skfs.

 

When running CNE1 the POC is calculated however plan/actual EV BCWS BCWP is not showing in the EV reports.

If I change the version and MM to Estimation on the L1 L2 WBSs and update the POC in CNPAWB these are calculated.

 

Any pointers would be great.

 

Cheers