IN CK11N overhead percentage change, percentage not pickup according to costing sheet

$
0
0

Hi,

 

In product costing CK11N  overhead percentage change, percentage not pickup accordingly assigned in cost sheet.

Example

Consumption   1000

Material Overhead 3% & too overhead 1% maintained in cost sheet but actual percentage not capture in CK11N.

but we are run another material system showing correct % but 3-4 material not showing properly.

In material master overhead group maintained and overhead % maintained properly.

 

please suggest me solution for this.

 

Regards

Pratik Khopkar