Hello
It is not mandatory to use MRP for the raw material, however, it is generally very useful.
There are some options to plan raw materials:
1 - Use a very simple reorder point MRP, for example, MRP type VB.
2 - Use a planning strategy for the components (strategy 70).
3 - Use MRP type PD and plan according to the dependent requirements.
BR
Caetano